Excavation Trip Calculator

Estimate whole trips using loose soil volume and usable capacity, with the conditions beside the result.

Estimate the material to haul

Bank volume is the excavation volume in the ground. Loose volume allows for expansion after excavation. Divide loose volume by usable loose capacity per trip, then round up to whole trips.

The starting 30% swell and 2.5 m³ capacity are examples, not universal soil or vehicle standards. Use suitable site/material information and confirm usable capacity with the transporter. This tool estimates volume-limited trips; it does not certify a vehicle's safe load.

Enter excavation and load assumptions

Starting example: a 10 × 10 × 1.5 m rectangular excavation, with all excavated soil removed.

Enter dimensions above 0 and up to 10,000 m, swell 0–200%, and usable loose capacity above 0 and up to 100 m³. Use up to three decimal places. These ranges are calculator guardrails, not engineering limits.

Cases and conditions

  • Sample case: 150 m³ bank volume, assumed 30% swell, 2.5 m³ usable loose capacity and all soil removed gives 78 trips. This is arithmetic for those inputs, not a guaranteed site count.
  • Site-data case: use site/material swell data and the transporter's usable loose capacity within safe and legal limits. The result remains a planning estimate, not a certified transport plan.
  • Different conditions: if soil is kept for backfill, do not use the all-soil-removal result as the final haul quantity. If weight or access reduces usable capacity, establish a suitable lower capacity before recalculating. This tool does not measure retained soil or calculate a weight-based capacity.

Formula and worked examples

Bank volume = length × width × depth.

Loose volume = bank volume × (1 + swell percentage ÷ 100).

Whole trips = loose volume ÷ usable loose capacity per trip, rounded up.

150 m³ bank volume example

10 × 10 × 1.5 = 150 m³ in the ground. At an assumed 30% swell: 150 × 1.3 = 195 m³ loose. At 2.5 m³ usable loose capacity: 195 ÷ 2.5 = 78 trips, if all material is removed.

A partial final load

2 m³ in the ground becomes 2.6 m³ loose at 30%. At 2.5 m³ usable capacity, the load ratio is 1.04 and the estimate is 2 physical trips. The last trip is only partly filled.

Before using the estimate

  • Capacity means usable cubic metres of loose material per trip, not bank-equivalent volume. Confirm it with the transporter.
  • The 30% starting swell is an editable planning example. Use suitable site/material data; this tool does not choose a universal soil factor.
  • The rectangular model does not include side slopes, working space, overbreak, groundwater or disposal restrictions. Dimensions must already describe the excavation to estimate.
  • No payload, axle, legal road-load or site-access checks are included. Follow the vehicle and local limits; never overload to meet this estimate.

Are inputs saved?

The calculation runs in your browser. This tool does not save the entered dimensions or arrange transport. Reloading resets the inputs.

Sources and related tool

FHWA distinguishes undisturbed excavation from expanded material in the transporting vehicle and calls for project-specific shrink/swell information. Caterpillar defines swell as the increase from bank to loose volume.

This page is a planning aid, not a measured site report, haulage quote or engineering certification.